Riverton Spray Park Construction

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Here is the latest project work in Riverton Heights Park

Project Address: Riverton Heights Park, 3011 S. 148th St., SeaTac

The current timeline looks like this:

    • Construction permitting approvals: July-November 2025
    • Construction bidding and contract approval: December-January 2026
    • Construction start: February 2026 to November 2026 (Mary and I need to discuss a more specific target for the spray park amenity completion and potential to incentivize the contractor to complete this amenity by June 2026 for potential opening). 

Project updates will be posted here and on our Speak Up site as project progresses.

Directly below is an image of the site plan completed at ____% - including the parking lot expansion. Further below are artist renderings of the future park updates.

 

 

 

 11586 RIVERTON HEIGHTS SPRAY PARK-10-30-2023-_Page_1

11586 RIVERTON HEIGHTS SPRAY PARK-10-30-2023-_Page_2

11586 RIVERTON HEIGHTS SPRAY PARK-10-30-2023-_Page_3

 

Project Contact Information
Michael Fitzpatrick, Deputy Parks & Recreation Director
mfitzpatrick@seatacwa.gov
206.973.4671

Page last updated in July 2025.